Fawley Power Station

Power Station Decommissioning Project 

Following on from our success at Didcot power station, in 2013 we were also contracted to Fawley Power Station in Hampshire for a cleaning project to their four boilers. Two of these boilers had been out of commission for 8 years and the other two were mothballed 17 years ago.

The project was to remove and clean non-asbestos insulation to the top deadspace, including cleaning and removal of all the boiler dusting systems, prior to the full decommissioning of the plant and subsequent demolition.

The project took 8 weeks to complete and was brought in on time and on budget.